Respond to a reactor high temperature abnormal situation
You are the panel operator for the reactor building on Panel C during a simulator exercise.
What has happened
Reactor 2 is 40 minutes into the acid addition on a ferric chloride batch when the cooling water supply pressure starts to fall because a cooling tower pump has tripped. The reactor temperature, normally held at 85 degrees, begins to climb towards the safe operating limit of 95 degrees with a trip at 100. Scrubber pH is drifting down as off-gassing increases. Within a few minutes there are twelve alarms on the panel. Tahlia Brennan is in the field near the reactor building. Wayne Djakovic is on the phone to the terminal. The alarm response manual gives response times for each alarm and the abnormal situation procedure sets out when to hold, reduce and shut down. The exercise ends with a shift handover.
Deliverables
- Timeline of alarms, actions and decisions with times
- Emergency shutdown decision record
- Incident register entry as a process safety event
- Completed shift handover report
Documents to use
Systems to use
Control Room Shift Log
Records every operating event, batch, reading, sample result, override and handover from the control room and the field for each shift.
Incident and Process Safety Event Register
Logs injuries, near misses, losses of containment, safety system activations, limit excursions and environmental events with tier, investigation and actions.
Units of competency
Current on training.gov.au for the Chemical, Hydrocarbons and Refining as at 10 September 2026.
PMAOPS402Respond to abnormal process situationsPMAOPS311Operate and troubleshoot reactors and reaction equipmentPMAOPS348Operate safety, protection and shutdown systemsPMAOPS236Monitor continuous process plantPMAOMIR210Control evacuation to muster pointQualifications
PMA30120Certificate III in Process Plant OperationsPMA40116Certificate IV in Process Plant TechnologyWhat to look for
Evidence guide
Look for the situation declared early, the outside operator protected before anything else, actions taken in the order and within the times in the alarm response manual, a shutdown decision that is made on the limit and the response time rather than delayed to save the batch, and a shutdown confirmed on the display and in the field. The event record and the handover must be complete and honest.