Prepare and isolate Reactor 1 for the bottom flange gasket replacement
You are an outside operator acting as isolation authority for Reactor 1.
What has happened
Reactor 1 has a weeping bottom outlet flange recorded as PSE-26-061 and the batch in it was transferred to T-204 on Monday. Maintenance will replace the gasket on Wednesday under permit PW-26-0784. The reactor still contains a heel of ferric sulfate, the acid charge line, the caustic scrubber return and the transfer line all connect to the vessel, and the agitator and bottom outlet valve are electrically driven. The isolation schedule for R-101 lists the isolation points, but one of the block valves on the transfer line is known to pass. Kylie Bassett's crew will fit their personal locks to the lockbox. Yolanda Ferreira wants the isolation to the spade or double block and bleed standard with the blind list reconciled and zero energy proven.
Deliverables
- Isolation plan listing every energy source and the standard applied
- Completed isolation certificate and blind list
- Zero energy proof record
- Permit register update
- De-isolation and leak test plan
Documents to use
Systems to use
Permit and Isolation Register
Tracks every permit to work, isolation certificate and blind from request to close-out and records permit audits.
Incident and Process Safety Event Register
Logs injuries, near misses, losses of containment, safety system activations, limit excursions and environmental events with tier, investigation and actions.
Control Room Shift Log
Records every operating event, batch, reading, sample result, override and handover from the control room and the field for each shift.
Units of competency
Current on training.gov.au for the Chemical, Hydrocarbons and Refining as at 10 September 2026.
PMASUP244Prepare and isolate plantPMAOPS347Create and conduct isolations in the workplacePMASUP245Break and make flanged joints using hand toolsPMAOPS311Operate and troubleshoot reactors and reaction equipmentPMAOPS280Interpret process plant schematicsQualifications
PMA30120Certificate III in Process Plant OperationsPMA40116Certificate IV in Process Plant TechnologyWhat to look for
Evidence guide
Every connected energy source must be identified, including the scrubber return and the electrical drives, and the passing valve must be dealt with by a spade or double block and bleed rather than accepted. Look for the flushings routed to a compatible destination, zero energy proven rather than assumed, a certificate that lists every tag and a return to service plan that includes a leak test before hazardous material is reintroduced.